抗滑桩模板施工专项方案【范本模板】

来源:筏尚旅游网
目 录

一、工程概况 ···················································································· 1 二、编制依据 ···················································································· 1 三、柱模板支撑计算书 ······································································· 1 (一)柱模板基本参数 ······································································ 1 (二)柱模板荷载标准值计算 ···························································· 2 (三)柱模板面板的计算 ··································································· 2

1.面板强度计算 ·································································································· 4 2.抗剪计算 ············································································································ 3 3.面板挠度计算 ···································································································· 5 (四)竖楞方木的计算 ········································································ 4

1.竖楞方木强度计算 ·························································································· 6 2。竖楞方木抗剪计算 ·························································································· 7 3.竖楞方木挠度计算 ···························································································· 6 (五)B方向柱箍的计算 ····································································· 8

1。柱箍强度计算: ································································································ 8 2。柱箍挠度计算 ································································································ 10 (六)B方向对拉螺栓的计算 ···························································· 9 (七)H方向柱箍的计算 ·································································· 9

1。柱箍强度计算 ································································································ 12 2。柱箍挠度计算 ································································································ 11 (八)H方向对拉螺栓的计算······························································································ 11

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

一、工程概况

雅砻江矿业有限责任公司黑牛洞铜矿工程名称 1500t/d采选工程场地平整及边坡支护工程 建设规模 建设单位 292根抗滑桩:规格为:1.4×2。1m,1.6×1。4m,1.8×2。7m, 雅砻江矿业有限责任公司 勘察单位 监理单位 四川省蜀通岩土工程公司 四川康立项目管理有限责任公司 建设地点 四川省甘孜州九龙县魁多乡江郎村 设计单位 四川省冶金设计研究院 施工单位 河南省地矿建设工程(集团)有限公司 本工程人工挖孔桩为矩形抗滑桩,桩入土埋深6~27m,出土部分采用安装模板后浇筑混凝土的方法施工,因此本工程不涉及模板支撑架、梁模板、板模板的设计及计算。

二、编制依据

1、 本工程设计施工图纸;

2、 国家现行结构荷载规范及建筑施工手册;

三、柱模板支撑计算书 (一)柱模板基本参数

柱模板的截面宽度:B=1500mm,B方向对拉螺栓2道, 柱模板的截面高度:H=1800mm,H方向对拉螺栓3道, 柱模板的计算高度:L =3000mm, 柱箍间距计算跨度:d = 450mm。

柱模板竖楞截面宽度60mm,高度80mm,间距300mm。 柱箍采用方木,截面80×100mm,每道柱箍1根方木,间距450mm.

柱箍是柱模板的横向支撑构件,其受力状态为受弯杆件,应按受弯杆件进行计算。

600270270

300800300云南景升建筑工程有限公司 1

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

柱模板计算简图

(二)柱模板荷载标准值计算

强度验算要考虑新浇混凝土侧压力和倾倒混凝土时产生的荷载;挠度验算只考虑新浇混凝土侧压力。

新浇混凝土侧压力计算公式为下式中的较小值:

其中:γ—— 混凝土的重力密度,取24。00kN/m3;

t -- 新浇混凝土的初凝时间,为0时(表示无资料)取200/(T+15),取5。714h;

T —- 混凝土的入模温度,取20.00℃; V -— 混凝土的浇筑速度,取3。00m/h;

H -- 混凝土侧压力计算位置处至新浇混凝土顶面总高度,取3.00m;

β1—— 外加剂影响修正系数,取1。00; β2—— 混凝土坍落度影响修正系数,取1。00。 根据公式计算的新浇混凝土侧压力标准值:F1=62.710kN/m2 实际计算中采用新浇混凝土侧压力标准值:F1=62。710kN/m2 倒混凝土时产生的荷载标准值:F2= 2。00kN/m2。 (三)柱模板面板的计算

云南景升建筑工程有限公司

2

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

面板直接承受模板传递的荷载,应该按照均布荷载下的三跨连续梁计算,计算如下

面板计算简图

1.面板强度计算 支座最大弯矩计算公式:

跨中最大弯矩计算公式:

其中:q -- 强度设计荷载(kN/m);

q = (1。2×62。710+1。4×2。00)×0。45 = 35.12kN/m 经过计算得到最大弯矩:M = 0.10×35.12×0.3×0。3=0.316kN.M

面板截面抵抗矩:W = 450×18×18/6=24300mm3

经过计算得到: σ = M/W = 0。316×106/24300 = 13。004N/mm2 面板的计算强度小于20.00N/mm2,满足要求! 2.抗剪计算

最大剪力的计算公式如下:

Q = 0。6qd

云南景升建筑工程有限公司

3

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

截面抗剪强度必须满足:

T = 3Q/2bh 〈 [T]

其中最大剪力:Q=0.6×0.3×35。12=6.322kN 截面抗剪强度计算值:

T=3×6322/(2×450×18)=1.171N/mm2 截面抗剪强度设计值 [T]= 1.30N/mm2 面板的抗剪强度计算满足要求! 面板的最大挠度满足要求! 3.面板挠度计算 最大挠度计算公式:

其中:q -- 混凝土侧压力的标准值, q = 62。710×0。45=28。22kN/m;

E ——面板的弹性模量,取3.00N/mm2; I-—面板截面惯性矩

I = 450×18×18×18/12=218700mm4; 经过计算得到:

v =0.677×(62.710×0.45)×3004/(100×3.00×218700) = 2358。593mm

[v] 面板最大允许挠度:[v] = 300/250 = 1.2mm; (四)竖楞方木的计算

云南景升建筑工程有限公司 4

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

竖楞方木直接承受模板传递的荷载,应该按照均布荷载下的三跨连续梁计算,计算如下:

竖楞方木计算简图

1.竖楞方木强度计算 支座最大弯矩计算公式:

跨中最大弯矩计算公式:

其中:q —— 强度设计荷载(kN/m);

q = (1.2×62。710+1。4×2。00)×0.3 = 23。42kN/m d为柱箍的距离:d = 450mm; 经过计算得到最大弯矩:

M = 0.10×23。42×0.45×0.45=0.474kN.M 竖楞方木截面抵抗矩: W = 60×80×80/6=000mm3 经过计算得到:

云南景升建筑工程有限公司

5

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

σ = M/W = 0。474×106/000 = 7.406N/mm2 竖楞方木的计算强度小于17N/mm2,满足要求!

2。竖楞方木抗剪计算 最大剪力的计算公式如下:

Q = 0.6qd

截面抗剪强度必须满足:

T = 3Q/2bh 〈 [T]

其中最大剪力:Q=0.6×0.45×23.42=6.323kN 截面抗剪强度计算值:

T=3×6323/(2×60×80)=1.976N/mm2 截面抗剪强度设计值 [T]=1。70N/mm2 竖楞方木抗剪强度计算满足要求! 3.竖楞方木挠度计算 最大挠度计算公式:

其中:q —- 混凝土侧压力的标准值,

q = 62.710×0。3=18。813kN/m;

E——竖楞方木的弹性模量,取10000N/mm2; I—-竖楞方木截面惯性矩

云南景升建筑工程有限公司 6

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

I = 60×80×80×80/12=2560000mm4; 经过计算得到:

v =0.677×(62.710×0.3)×4504/ (100×10000×2560000) = 0。204mm

[v] 竖楞方木最大允许挠度,[v] = 450/250 = 1.8mm; 竖楞方木的最大挠度满足要求! (五)B方向柱箍的计算

本算例中,柱箍采用方木,截面惯性矩I和截面抵抗矩W分别为: W = 8×10×10/6 = 133.333cm3 I = 8×10×10×10/12 = 666.667cm4

10.kN 10.kN10.kN

A410410B方向柱箍计算简图 B其中:P -- 竖楞方木传递到柱箍的集中荷载(kN); P = (1.2×62.710+1。4×2.00)×0。3 × 0。45 = 10.kN 经过连续梁的计算得到:

5.345.345.2 5.2云南景升建筑工程有限公司

5.345.347

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

B方向柱箍剪力图(kN) 0.655 0.748 0.748B方向柱箍弯矩图(kN.m)

0.0.0040040.0040.0040.004B方向柱箍变形图(kN。m)

最大弯矩:M = 0.748kN.m 最大支座力:N = 20。94kN 最大变形:v = 0.004mm 1。柱箍强度计算: 柱箍截面强度计算公式:

=M/W 〈 [f]

其中:M —- 柱箍杆件的最大弯矩设计值, M = 0.748kN.m;

W -- 弯矩作用平面内柱箍截面抵抗矩,

云南景升建筑工程有限公司

8

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

W = 133.333cm3;

柱箍的强度设计值(N/mm2): [f] = 17 B边柱箍的强度计算值:f = 5.61N/mm2; B边柱箍的强度验算满足要求! 2.柱箍挠度计算

经过计算得到:v =0.004mm

[v] 柱箍最大允许挠度,[v] = 300/250 = 1.2mm; 柱箍的最大挠度满足要求! (六)B方向对拉螺栓的计算 计算公式:

N < [N] = fA

其中:N —- 对拉螺栓所受的拉力; A -- 对拉螺栓有效面积 (mm2);

f —— 对拉螺栓的抗拉强度设计值,取170N/mm2; 对拉螺拴的强度要大于最大支座力20。94kN。 经过计算得到B方向对拉螺拴的直径要大于13mm! (七)H方向柱箍的计算

10.kN 10.kN10.kNA 510510B H方向柱箍计算简图

云南景升建筑工程有限公司

9

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

其中:P -— 竖楞方木传递到柱箍的集中荷载(kN);

P = (1。2×62。710+1。4×2。00)×0。3 × 0.45 = 10。kN 经过连续梁的计算得到:

6.144.44.4 4.44.46.14 H方向柱箍剪力图(kN) 0.919

0.9230.923H方向柱箍弯矩图(kN.m) 0.0.0101 0.010.01H方向柱箍变形图(kN.m)

最大弯矩:M = 0.923kN。m 最大支座力:N = 22。82kN 最大变形:v = 0。01mm

云南景升建筑工程有限公司

10

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

1.柱箍强度计算 柱箍截面强度计算公式:

=M/W 〈 [f]

其中:M -— 柱箍杆件的最大弯矩设计值, M = 0.923kN。m;

W -- 弯矩作用平面内柱箍截面抵抗矩, W = 133。333cm3;

柱箍的强度设计值(N/mm2): [f] = 17 H边柱箍的强度计算值 f = 6.92N/mm2; H边柱箍的强度验算满足要求! 2。柱箍挠度计算

经过计算得到:v =0。01mm

[v] 柱箍最大允许挠度,[v] = 400/250 = 1。6mm; 柱箍的最大挠度满足要求! (八)H方向对拉螺栓的计算 计算公式:

N < [N] = fA

其中:N -— 对拉螺栓所受的拉力; A -- 对拉螺栓有效面积 (mm2);

f -— 对拉螺栓的抗拉强度设计值,取170N/mm2; 对拉螺拴的强度要大于最大支座力22。82kN。 经过计算得到H方向对拉螺拴的直径要大于13mm!

云南景升建筑工程有限公司

11

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

(九)模板工程 1、模板系统

根据本工程特点,模板采用组合钢模板拼装为主,辅以木枋、层板模板系统。加固支撑系统选用钢管、扣件式加固支撑系统。

2、施工方法:

模板采用组合钢模板,为保证模板的竖向刚度,组合钢模板采用竖向拼装,相邻模板横向拼缝相互错开。

模板加固、支撑系统采用钢管、扣件加固、支撑系统(示意图:模板平面图;模板加固、支撑系统平面图;模板加固、支撑系统立面图).模板加固抱箍竖向间距500,模板支撑架竖向步距不大于1600,模板支撑架兼作施工脚手架。

云南景升建筑工程有限公司

12

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

上段模板支架的刚度、稳定性须依靠下段柱的支撑,因此,为保证模板支架的稳固、刚度,中途不拆除支架与柱的拉结抱箍,待整棵柱混凝土全部浇完后再从上至下拆除支架及模板,模板加固抱箍可先行拆除周转。如确需拆除模板用于周转,模板拆除后,必须重新进行支架与柱的拉结并确保拉结稳固.

云南景升建筑工程有限公司

13

雅砻江矿业有限责任公司黑牛洞铜矿1500t/d采选工程场地平整及边坡支护工程抗滑桩及挡土墙

在桩及挡土板的截面短向增设对拉螺栓,以抵抗混凝土对模板的侧向压力。螺栓横向间距300,竖向排距500,最上一排螺栓距模板上口距离不大于800(根据混凝土对模板的侧向压力沿高度方向逐渐减小的特点,模板底部必须加设对拉螺栓,顶部不设对拉螺栓。

3质量控制措施

a、模板工程是整个砼工程的中心环节,应精心设计、精心制作、精心施工。模板的加工制作和安装允许偏实测合格率达到80%以上,且偏差值不得大于允许偏差值的150%。柱模板安装过程中认真抄平、校正,并预先弹出模板控制线,确保模板安装位置及断面准确。

b、柱头模拼装完后,应拉通线校正,保证侧模方正、顺直、垂直,先拉线校正水平支撑,铺设后拉线检查模板表面是否平整、顺直。

c、质检员负责认真对模板的截面尺寸、轴线位移、标高、模内情况、脱模剂的涂刷等进行技术复核及质量的检验评定。

d、浇筑砼前浇水湿润模板,浇筑过程杜绝荷载集中。 e、拆模时不得死撬硬砸,要按先装后拆,后装先拆的顺序拆模,拆下的模板在运输、堆放的过程中,注意保护,避免碰坏,以增加模板的周转次数。